Construction Status

Wintergreen
As on 31st Aug 2017

Construction Status

Wintergreen
As on 31st Aug 2017
Wintergreen A-Wing
Blockwork – 42nd Floor In Progress
Concealed Plumbing Work – 9th Floor In Progress
Kitchen Platform And Wall Tiles – 5th Floor Completed
Toilet Wall Tilling Work – 5th Floor Completed
Basement Slab Shuttering In Progress (East Side Of Wing A )
Wintergreen B-Wing
Above Terrace Work In Progress
Blockwork – 7th Floor In Progress
Wintergreen C-Wing
Above Terrace Work In Progress (Lmr Top Slab In Progress)
External Plaster In Progress (West Side)
Door Frame Fixing - 10th Floor In Progress
Gypsum Plaster - Ceiling Plaster Completed Upto 10th Floor
Toilet Waterproofing (Base Coat) – 4th And 5th Floor In Progress
Podium Slab Reinforcement Tieing In Progress
(South Side Of Wing C)
Wintergreen D-Wing
37th Floor Slab In Progress
Blockwork – 26th Floor In Progress
Door Frame Fixing – 14th Floor In Progress
Gypsum Plaster – 8th Floor In Progress
Toilet Waterproofing (Base Coat)- 5th Floor Completed
External Plaster In Progress (Courtyard Area)
Wintergreen E-Wing
Blockwork – 6th Floor In Progress
Wintergreen F-Wing
Above Terrace Work In Progress
External Plaster In Prorgress (Courtyard Area)